Turnkey Electrical Project

Customer

Hema Driveline & Hydraulics India Pvt. Ltd., Turkish Mnc In Midc, Chakan Pune

Project Category

Auto Ancillary Plant

Project Budget

52 Lacs

Project Description

LT Installation Work

CUSTOMER REQUIREMENT:
Low Voltage Installation Job

WHAT WE DID:
Low Voltage ( LV ) Installation Work as follows:Preparation of Comprehensive Power Distribution Scheme comprising of Single Line Diagram(SLD), Cable Schedule, Earthing Schedule, Electrical Equipment Layout, GA Drawings etc., Sizing of DG Sets. Design, Manufacture, Supply, Installation & Commissioning of Power Control Centre(PCC), Power Distribution Boards, Automatic Power Factor Correction Panel (APFC), Plug Socket Box etc. Fabrication of supports, Fixing of GI perforated Cable Trays, Laying of GI earthing flats, Laying of LT cables & End terminations.Earthing Stations Confirming to IS-3043 & Providing Earthing to all Equipment.

RESULT:
Commissioned

Project Status : Completed on 7 June 2015